Mar 11, 2020 | Construction Updates
This spring, construction of a new river water pumphouse for the LNG Canada Project will begin. As part of the LNG processing plant design, water will be sourced from the Kitimat River and will be used for multiple areas of the project during both construction and...
Feb 28, 2020 | News Updates
JGC Fluor BC LNG Joint Venture hereby gives notice for the installation of a 45-meter temporary antenna structure. This notification is in accordance with ISED’s (Innovation, Science and Economic Development Canada) federally regulated process, Radio communication and...
Feb 28, 2020 | News Updates
JGC Fluor BC LNG Joint Venture hereby gives notice for the installation of a 80-meter antenna structure. This notification is in accordance with ISED’s (Innovation, Science and Economic Development Canada) federally regulated process, Radiocommunication and...
Feb 13, 2020 | News Updates
Monday, February 17 is Family Day and our office will be closed. We re-open to the public on Tuesday.
Feb 10, 2020 | Construction Updates
Beginning the week of February 10, site preparation activities (tree felling, clearing, and grubbing) will begin for construction of a new river water pumphouse, water line, and substation for the LNG Canada Project. As part of the LNG processing plant design, water...
Jan 29, 2020 | News Updates
The JGC Fluor Project Resource Centre is closed Thursday, January 30, 2020. We apologize for any inconvenience.
Jan 22, 2020 | Construction Updates
Work on the LNG Canada Project is well underway and JGC Fluor will continue to ramp up construction activities in 2020, including piling throughout the project site. Piles (steel poles or sheets) are being used as deep foundations to ensure the stability of temporary...
Jan 13, 2020 | Construction Updates
Starting as early as January 14, work will continue for the twinning of Alcan Bridge. Crews successfully lifted the new bridge structure into place on January 10 and will now begin to install the deck. Work will occur from 7:30 a.m. to 4 p.m.—seven days per week—and...
Jan 8, 2020 | Construction Updates
As part of the widening of Alcan Bridge, access to Alcan Way will be closed in both directions between Ocelot Road junction and the LNG Canada site west gate the night of January 10, 2020 from 20:00 to 00:00. JGC Fluor (JFJV) will transport and install the new,...
Jan 3, 2020 | Construction Updates
Beginning as early as January 6, additional truck traffic can be expected along Haisla Boulevard between Eurocan Way and Ocelot Road. Trucks will be hauling aggregate from Sandhill to the LNG Canada Project site. This route will be utilized while upgrades are made to...