Jan 22, 2020 | Construction Updates
Work on the LNG Canada Project is well underway and JGC Fluor will continue to ramp up construction activities in 2020, including piling throughout the project site. Piles (steel poles or sheets) are being used as deep foundations to ensure the stability of temporary...
Jan 13, 2020 | Construction Updates
Starting as early as January 14, work will continue for the twinning of Alcan Bridge. Crews successfully lifted the new bridge structure into place on January 10 and will now begin to install the deck. Work will occur from 7:30 a.m. to 4 p.m.—seven days per week—and...
Jan 8, 2020 | Construction Updates
As part of the widening of Alcan Bridge, access to Alcan Way will be closed in both directions between Ocelot Road junction and the LNG Canada site west gate the night of January 10, 2020 from 20:00 to 00:00. JGC Fluor (JFJV) will transport and install the new,...
Jan 3, 2020 | Construction Updates
Beginning as early as January 6, additional truck traffic can be expected along Haisla Boulevard between Eurocan Way and Ocelot Road. Trucks will be hauling aggregate from Sandhill to the LNG Canada Project site. This route will be utilized while upgrades are made to...
Nov 21, 2019 | Construction Updates
Starting the week of December 2, 2019, a bathymetric survey of Kitimat River will take place near the existing Eurocan water intake. Bathymetry is the process of mapping underwater topography of the ground beneath rivers, ponds, lakes, and oceans. The survey will be...
Nov 19, 2019 | Construction Updates
Work is now underway to construct the LNG Canada Project Materials Offloading Facility (MOF), which is located between Rio Tinto’s Terminal B and the former Methanex causeway. As part of this work, piling will occur intermittently between 7 a.m. and 10 p.m.—seven days...
Nov 14, 2019 | Construction Updates
Starting today (Nov. 14), some noise, and traffic delays up to 15 minutes, can be expected while piling activities take place at Alcan Bridge. This work will occur from 7:30 a.m. to 4 p.m. and is expected to be complete by Monday, Nov 18. Traffic controllers will be...
Nov 9, 2019 | Construction Updates
Transportation notification: Alcan Road On Nov.10 & 11, between 8:30 a.m. and 2 p.m., some traffic delays up to 15 minutes can be expected, while piles are offloaded and hoisted by crane at Alcan Bridge. Flaggers will be in place to safely manage traffic...
Nov 9, 2019 | Construction Updates
Transportation notification: Alcan Road On Nov.10 & 11, between 8:30 a.m. and 2 p.m., some traffic delays up to 15 minutes can be expected, while piles are offloaded and hoisted by crane at Alcan Bridge. Flaggers will be in place to safely manage traffic...
Oct 11, 2019 | Construction Updates
There will be Hydrovac work and Hot Tap installs just after the curve of Harbour Road and Ocelot Road, west of the main LNG Canada site security gate. This will take place from 10 a.m., October 11, 2019, to 5:00 p.m., October 15, 2019. One lane will be reduced in...
Oct 9, 2019 | Construction Updates
JFJV’s sub-contractor, Ledcor-Haisla will be removing trees at the substation near Ocelot Road. This will take place from 8:00 a.m., October 9, 2019, to 10:00 a.m., October 10, 2019. There may be lane restrictions and traffic interruptions as the excavator...
Sep 13, 2019 | Construction Updates
Starting as early as September 16, JGC Fluor (JFJV) will be performing routine maintenance on an existing river water intake, located approximately 250 metres upstream of the Kitimat River Hatchery. The intake provides raw water to the LNG Canada Project site. Work...