Oct 10, 2019 | News Updates
Monday, October 14 is Thanksgiving Day and our office will be closed. We will be open again to the public on Tuesday. Happy Thanksgiving!
Oct 9, 2019 | Construction Updates
JFJV’s sub-contractor, Ledcor-Haisla will be removing trees at the substation near Ocelot Road. This will take place from 8:00 a.m., October 9, 2019, to 10:00 a.m., October 10, 2019. There may be lane restrictions and traffic interruptions as the excavator...
Sep 22, 2019 | News Updates
Please join us JGC Fluor, LNG Canada, and Coastal GasLink at an Open House and Job Fair to learn about progress made during the first year of construction, and current and upcoming opportunities for employment. October 1 – Riverlodge, 654 Columbia Avenue,...
Sep 20, 2019 | News Updates
YOUR PLACE is a tuition-free training designed to help women start – and succeed – in the skilled trades, including a direct opportunity for employment on the LNG Canada project.
Sep 17, 2019 | News Updates
We’ll be at the Terrace Sportsplex September 18 & 19, 2019 ready to chat with you about the different job opportunities available on the LNG Canada Project.
Sep 13, 2019 | Construction Updates
Starting as early as September 16, JGC Fluor (JFJV) will be performing routine maintenance on an existing river water intake, located approximately 250 metres upstream of the Kitimat River Hatchery. The intake provides raw water to the LNG Canada Project site. Work...
Sep 10, 2019 | Construction Updates
Open burning for the LNG Canada Project has been suspended. Winds have shifted from the south, so we have stopped feeding burn piles. Active piles will be closely monitored and allowed to burn out. If you have an inquiry, please send it to info@jfjvkitimat.com or call...
Sep 10, 2019 | Construction Updates
JGC Fluor (JFJV) will soon begin work to construct two cofferdams along the embankment of the Kitimat River. These cofferdams will create watertight enclosures that will be pumped dry and allow for the installation of two inlet portals. The cofferdams will be built...
Sep 9, 2019 | Construction Updates
Open burning for the LNG Canada Project has resumed. The custom venting index for the project has returned to “good” and is forecasted to remain good today and tomorrow. A test pile has been lit and is performing as expected. We will continue to monitor...
Sep 1, 2019 | Construction Updates
Due to today’s unfavourable venting conditions, we’ve stopped open burning activities and no longer feeding the fire on the LNG Canada project site. Thank you for your patience and understanding.