Aug 28, 2019 | Construction Updates
We’ll begin by lighting a test pile, which will help inform our burning program going forward. All burning will be carefully planned and monitored, including: the timing; size and location of the burn piles, and the venting index that determines when weather is...
Aug 28, 2019 | Construction Updates
JGC Fluor (JFJV) is beginning work to twin Alcan Bridge, which is currently being used to transport aggregate for the LNG Canada Project from Sandhill to site along the North Haul Road. Another bridge will be built beside the existing bridge to allow for increased...
Aug 24, 2019 | News Updates
Monday, September 2 is a statutory holiday and our office will be closed. We will be open again to the public on Tuesday.
Aug 17, 2019 | Construction Updates
JGC Fluor (JFJV) will be resuming tree clearing activities and woody debris management —including open burning—for the LNG Canada Project. These activities were temporarily put on hold earlier this spring/summer due to bird nesting season, which ends August 17. As...
Aug 3, 2019 | News Updates
Monday, August 5th is a statutory holiday and our office will be closed. We will be open again to the public on Tuesday.
Jul 30, 2019 | News Updates
JGC Fluor (JFJV) is excited to announce that we’re officially opening the doors to our Project Resource Centre. This community liaison office is a central location for people seeking information on the LNG Canada project and will handle questions related to...
Jun 25, 2019 | Construction Updates
The first phase of open burning for the LNG Canada Project is close to completion. Some intermittent burning may occur in the coming weeks, dependent on the venting index which indicates when weather conditions are suitable to burn. If you have an inquiry, please send...
Jun 17, 2019 | News Updates
VANCOUVER, B.C.– LNG Canada and its prime contractor, JGC Fluor BC LNG JV (JGC Fluor), today announced the launch of YOUR PLACE, a province-wide workforce development program aimed at attracting, recruiting, training, supporting and employing women to work in...
Jun 4, 2019 | Construction Updates
Open burning at the LNG Canada project site will resume once favourable venting conditions are confirmed in accordance with the permits issued by the District of Kitimat (DoK). If you have an inquiry, please send it to info@jfjvkitimat.com or call the JFJV community...
May 25, 2019 | Uncategorized
JGC Fluor (JFJV) is advancing the engineering and construction of the LNG Canada Project, which includes conducting test piling activities at the project site this spring/summer. Piles (steel poles) will be used throughout the construction of the project and serve as...